Time and work questions ask how long a job takes when people, machines or pipes work at different speeds. They appear in the aptitude part of TNPSC Group 4 and in the Mathematics sections of RRB NTPC, RRB Group D and SBI Clerk and PO. Most of them come down to one concept: work done per day. Below, that concept becomes the LCM method, then six formulas based on it with an example each, and then 15 exam-type questions with full solutions.
Where time and work questions come up
Time and work is one topic inside a larger maths section. Section sizes in the latest notifications, as listed in our percentage shortcuts guide:
Exam | Section | Questions in the section |
|---|---|---|
TNPSC Group 4 | Part C, Aptitude unit | 15 of 200 |
RRB NTPC | Mathematics | 30 of 100 (CBT-1) |
RRB Group D | Mathematics | 25 of 100 |
SBI Clerk prelims | Numerical Ability | 35 of 100 |
No exam board tells you how many time and work questions it will set. Expect one or two in a section, sometimes in the form of a pipes and cisterns question or a wages problem. Full topic lists: Group 4, RRB NTPC, RRB Group D and SBI Clerk and PO.
The one idea: work done per day
If A can finish a job in 12 days, A does 1/12 of the job every day. If B takes 18 days, B does 1/18 a day. Working together, they do 1/12 + 1/18 of the job a day, and the time taken is 1 divided by that.
Adding fractions under exam pressure is where mistakes happen, so turn the job into whole units instead. This is the LCM method:
Take the LCM of all the given days (or hours). Call that the total work, in units.
Divide the total by each person's days to get their units per day.
Add the units per day of everyone working together (subtract for anyone undoing work, like a leak).
Total units ÷ units per day = days taken.
Worked example: A takes 12 days and B takes 18 days. The LCM of 12 and 18 is 36, so the job is 36 units. A does 36 ÷ 12 = 3 units a day and B does 36 ÷ 18 = 2. Together that is 5 units a day, so the job takes 36 ÷ 5 = 7.2 days, or 7 1/5 days.
Every formula below is this method in a shorter form.
Six time and work formulas
Formula 1: two people together
If A takes a days and B takes b days, together they take ab ÷ (a + b) days.
Example: 12 and 18 days → (12 × 18) ÷ 30 = 216 ÷ 30 = 7.2 days. Same answer as the LCM method. For three or more people, use the LCM method; the product formula gets messy.
Formula 2: efficiency is the opposite of time
If A is twice as efficient as B, A takes half the time. Efficiency ratio 2 : 1 means time ratio 1 : 2.
Example: A is twice as fast as B, and together they finish in 14 days. Take A's daily work as 2 units and B's as 1. Together that is 3 units a day for 14 days, so the job is 42 units. B alone takes 42 ÷ 1 = 42 days, and A takes 42 ÷ 2 = 21 days.
Formula 3: men, days and hours
When the job stays the same, M₁ × D₁ × H₁ = M₂ × D₂ × H₂, where M is the number of workers, D the days and H the hours per day. If the amount of work changes too, divide each side by its work: M₁D₁H₁ ÷ W₁ = M₂D₂H₂ ÷ W₂.
Example: 15 men working 8 hours a day finish a job in 12 days. How many days will 20 men working 6 hours a day take? 15 × 8 × 12 = 1,440 = 20 × 6 × D, so D = 1,440 ÷ 120 = 12 days.
Formula 4: someone leaves or joins midway
Find the work done before the change, subtract it from the total, and finish the rest at the new rate.
Example: A takes 20 days and B 30 days. They work together for 6 days, then A leaves. The job is 60 units (LCM); A does 3 a day and B does 2. In 6 days they do 5 × 6 = 30 units. B finishes the other 30 units at 2 a day, in 15 days.
Formula 5: pipes and cisterns
A pipe that fills is a worker; a pipe or leak that empties is a worker going backwards. Add the fillers and subtract the emptiers.
Example: pipe A fills a tank in 6 hours and pipe B empties it in 9 hours. Take the tank as 18 units. A adds 3 an hour and B removes 2, so the tank gains 1 unit an hour and is full in 18 hours.
Formula 6: sharing wages
When people work together for the whole job, they are paid in the ratio of the work they do, which is the ratio of their efficiencies.
Example: A takes 10 days and B 15 days; together they earn ₹4,500 for the job. In 30 units, A does 3 a day and B 2, so the pay splits 3 : 2. A gets 4,500 × 3/5 = ₹2,700 and B gets ₹1,800.
15 solved time and work questions
Try each one before reading the solution. Most should take under a minute once the LCM step is automatic.
1. A can finish a job in 15 days and B in 10 days. How long will they take together?
Solution: 15 × 10 ÷ (15 + 10) = 150 ÷ 25 = 6 days.
2. A and B together finish a job in 8 days. A alone takes 12 days. How long does B alone take?
Solution: Take the job as 24 units (LCM of 8 and 12). A + B do 3 a day and A does 2, so B does 1. B alone takes 24 days.
3. A, B and C can do a job in 12, 15 and 20 days. How long will they take together?
Solution: Job = 60 units. A does 5, B 4 and C 3 a day: 12 units a day. 60 ÷ 12 = 5 days.
4. A and B can finish a job in 10 days, B and C in 15 days, and A and C in 12 days. How long will A, B and C take together?
Solution: Job = 60 units. A + B = 6, B + C = 4, A + C = 5 units a day. Adding all three pairs counts each person twice: 2(A + B + C) = 15, so A + B + C = 7.5 units a day. 60 ÷ 7.5 = 8 days.
5. 20 men can build a wall in 18 days. How many men are needed to build it in 12 days?
Solution: 20 × 18 = 360 man-days. 360 ÷ 12 = 30 men.
6. 10 men working 6 hours a day finish a job in 16 days. How many days will 12 men working 8 hours a day take?
Solution: 10 × 6 × 16 = 960 = 12 × 8 × D. D = 960 ÷ 96 = 10 days.
7. 16 men can complete a job in 25 days. After 10 days, 4 men leave. How many more days will the rest take to finish?
Solution: The job is 16 × 25 = 400 man-days. In 10 days, 160 are done, leaving 240. The 12 remaining men need 240 ÷ 12 = 20 more days.
8. A is 50% more efficient than B. B alone takes 30 days. How long will A and B take together?
Solution: Take B's daily work as 2 units; A's is 3 (50% more). The job is 30 × 2 = 60 units. Together they do 5 a day: 60 ÷ 5 = 12 days.
9. A can do a job in 24 days. A works for 6 days, and B finishes the rest in 27 days. How long would B take to do the whole job alone?
Solution: In 6 days A does 6/24 = 1/4 of the job, leaving 3/4. B does 3/4 in 27 days, so the whole job takes B 27 × 4/3 = 36 days.
10. A and B can do a job in 12 and 18 days. They work together for 4 days, then A leaves. How long does B take to finish?
Solution: Job = 36 units. A does 3 and B 2 a day. In 4 days they do 20 units, leaving 16. B finishes them in 16 ÷ 2 = 8 days.
11. Pipe A fills a tank in 20 minutes and pipe B in 30 minutes. If both are opened, how long does the tank take to fill?
Solution: 20 × 30 ÷ 50 = 12 minutes.
12. Two taps fill a tank in 12 hours and 15 hours. A waste pipe empties the full tank in 20 hours. If all three are opened together, how long will the tank take to fill?
Solution: Tank = 60 units. The taps add 5 and 4 an hour and the waste pipe removes 3: net 6 an hour. 60 ÷ 6 = 10 hours.
13. A pipe fills a tank in 8 hours, but because of a leak it takes 10 hours. How long would the leak take to empty the full tank?
Solution: Tank = 40 units. The pipe adds 5 an hour, but the tank actually gains 4 (40 ÷ 10), so the leak removes 1 an hour. It empties the full tank in 40 hours.
14. A, B and C can do a job in 6, 8 and 12 days. Working together, they are paid ₹3,600. What is C's share?
Solution: Job = 24 units; A, B and C do 4, 3 and 2 a day. Pay splits 4 : 3 : 2, so C gets 3,600 × 2/9 = ₹800.
15. A can do a job in 10 days and B in 15 days. They work on alternate days, A starting. In how many days is the job finished?
Solution: Job = 30 units; A does 3 and B 2. Every two days they do 5 units. Six such pairs finish 30 units exactly, so the job takes 6 × 2 = 12 days. (When the total doesn't divide evenly, finish the last few units day by day.)
Common mistakes in time and work questions
Adding days instead of work. A takes 12 days and B 18 days does not make 30 days, or 15 days. Add the daily work, never the days.
Splitting wages by days. Pay follows work done, so it is the inverse of the days (see Formula 6).
Forgetting hours a day. If the hours per day change, they belong in M × D × H.
Adding a leak. A leak or waste pipe is negative work. Subtract it.
Mixing units. If one pipe is in minutes and another in hours, convert first.
Practise until the LCM step is automatic
The method is short, but speed only comes from repetition. Aim to set up the LCM within ten seconds of reading a question. Thervu's free mock tests cover the full syllabus, maths included, in Tamil or English, and are marked the moment you submit. The question banks for TNPSC Group 4, RRB NTPC, RRB Group D, TN Police SI and SBI Clerk and PO also have a separate Time & Work topic; picking a single topic is on the Pro plan.
Next in the aptitude series: percentage shortcuts and TNPSC shortcuts in Tamil.
Frequently asked questions
What is the formula for time and work?
If A finishes a job in a days and B in b days, together they take ab ÷ (a + b) days. Behind every formula is one idea: a person who takes n days does 1/n of the job each day, so you add the daily work of everyone working together.
What is the LCM method in time and work?
Take the LCM of the given days as the total work in units. Each person's daily work is that total divided by their days. For 12 and 18 days, the LCM is 36 units, A does 3 a day, B does 2, so together they need 36 ÷ 5 = 7.2 days. It avoids fractions entirely.
How do you solve pipes and cistern questions?
The same way as time and work. A filling pipe adds its share of the tank each hour, an emptying pipe or leak subtracts its share. Take the LCM of the hours as the tank's capacity in units, add the inlets, subtract the outlets, and divide.
Is time and work in the TNPSC Group 4 syllabus?
Yes. Time and work is listed in the aptitude part of the Group 4 syllabus, along with simplification, percentage, HCF and LCM, ratio and proportion, interest, area and volume. It is also a regular Mathematics topic in RRB NTPC, RRB Group D and SBI Clerk and PO.
How is wages divided in time and work questions?
When people work together for the same number of days, wages are shared in the ratio of the work each one does, which is the ratio of their daily work (efficiency), not the ratio of their days. A 10-day worker and a 15-day worker split pay 3:2.
Related guides
Profit and Loss Questions: All Formulas, Short Tricks and 15 Solved Problems for TNPSC, Railway and Bank Exams
Cost price, selling price and marked price explained, every profit and loss formula including percentages and discounts, five short tricks, and 15 solved word problems with full working.
· 6 min read
Ratio and Proportion Questions: Formulas, Mean Proportional, Tricks and 18 Solved Problems for TNPSC, Railway and Bank Exams
What ratio and proportion mean, every formula exams use (mean, third and fourth proportional, continued proportion), five tricks, the question types that repeat, and 18 solved problems with full working.
· 8 min read
LCM and HCF Questions: How to Find Them, the Formulas and 15 Solved Problems for TNPSC, Railway and Bank Exams
How to find HCF and LCM by prime factors and by division, the formulas that link them, the six question types exams keep asking, and 15 solved problems with full working.
· 7 min read